UK renewable project intelligence · REPD 10486
Newmarket Road, Bottisham - Battery Energy Storage
Ridge Clean Energy Limited · Battery · Eastern
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantRidge Clean Energy Limited
RegionEastern
CountyCambridgeshire
CountryEngland
Planning authorityEast Cambridgeshire
Planning reference22/01291/ESF
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal98/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 98% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- Observed multi-stage progression
Risks and missing evidence
- Long time in current stage