UK renewable project intelligence · REPD 10811
Oldmedow Road - Solar Panels
Sensient Colors · Solar Photovoltaics · Eastern
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologySolar Photovoltaics
Operator or applicantSensient Colors
RegionEastern
CountyNorfolk
CountryEngland
Planning authorityKing's Lynn and West Norfolk
Planning reference22/00389/PART14
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal50/100Typical relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 50% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- Observed multi-stage progression
Risks and missing evidence
- Long time in current stage