UK renewable project intelligence · REPD 11473
Well Street - Battery Storage
Larkfleet Group · Battery · Scotland
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantLarkfleet Group
RegionScotland
CountyStrathclyde
CountryScotland
Planning authorityRenfrewshire
Planning reference23/0018/PP
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal97/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 97% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- Observed multi-stage progression
Risks and missing evidence
- Long time in current stage