UK renewable project intelligence · REPD 13158
Thornbury, West Ashland - Solar Photovoltaic System
Dominos Pizza Uk & Ireland Limited · Solar Photovoltaics · South East
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologySolar Photovoltaics
Operator or applicantDominos Pizza Uk & Ireland Limited
RegionSouth East
CountyBuckinghamshire
CountryEngland
Planning authorityMilton Keynes
Planning reference22/03119/PRIOR
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal70/100Typical relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 70% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
Risks and missing evidence
- Long time in current stage