UK renewable project intelligence · REPD 01330
Cefn Betingau Farm
Wessex Solar Energy · Solar Photovoltaics · Wales
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologySolar Photovoltaics
Operator or applicantWessex Solar Energy
RegionWales
CountyWest Glamorgan
CountryWales
Planning authorityCarmarthenshire
Planning reference2013/0865
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Became operational
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
This planning record is outside the current active forecast universe. Its public project evidence remains searchable and comparable.
Positive public evidence
No additional positive signal is recorded.
Risks and missing evidence
No additional public-data warning is recorded.