UK renewable project intelligence · REPD 13761
Fair Park Solar Farm
Downing Renewable Developments Llp · Battery · South West
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantDowning Renewable Developments Llp
RegionSouth West
CountyCornwall
CountryEngland
Planning authorityCornwall
Planning referencePA23/02629
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal92/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 92% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- Observed multi-stage progression
Risks and missing evidence
- No major public-data warning detected