UK renewable project intelligence · REPD 14594
North Court Farm, Redwick - Wind Turbine
Clean Earth Energy Limited · Wind Onshore · Wales
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantClean Earth Energy Limited
RegionWales
CountyGwent
CountryWales
Planning authorityNewport
Planning referenceDM/2023/01045
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal3/100Lower relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 3% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- No strong positive signal in public data
Risks and missing evidence
- Early development stage
- Long time in current stage