SSE Taynuilt Substation - Battery Energy Storage

Downing Energy Development Company Limited · Battery · Scotland

Reported capacity49.9 MWInstalled Capacity (MWelec) in the public REPD record
Development stageAwaiting ConstructionCurrent short status in the latest source snapshot
Screening score70/100Low heuristic screening risk

Planning record

Project Evidence

Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.

TechnologyBattery
Operator or applicantDowning Energy Development Company Limited
RegionScotland
CountyStrathclyde
CountryScotland
Planning authorityArgyll and Bute
Planning reference24/02083/PP
CfD allocation roundNot reported

Planning history

Planning Timeline

  • Planning submitted
  • Planning granted
  • Latest public record

Time to operation

Delivery Signal

Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.

Two-year signal86/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
Ranking signal only · Moderate public-data coverage

The score is a percentile rank, not a 86% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.

Positive public evidence

  • Construction has started

Risks and missing evidence

  • No major public-data warning detected