Planning reference24/00311/FUL
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Construction started
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal82/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 82% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
Risks and missing evidence
- No major public-data warning detected