UK renewable project intelligence · REPD 00252
PwllfaWatkin AD Plant (Waste AD)
Waste Recycling Group · Anaerobic Digestion · Wales
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyAnaerobic Digestion
Operator or applicantWaste Recycling Group
RegionWales
CountyWest Glamorgan
CountryWales
Planning authorityNeath Port Talbot
Planning referenceP2011/1063
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
This planning record is outside the current active forecast universe. Its public project evidence remains searchable and comparable.
Positive public evidence
No additional positive signal is recorded.
Risks and missing evidence
No additional public-data warning is recorded.