UK renewable project intelligence · REPD 03721
Upper Vaunces Wind Farm
TCI Renewables · Wind Onshore · Eastern
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantTCI Renewables
RegionEastern
CountyNorfolk
CountryEngland
Planning authoritySouth Norfolk
Planning reference2010/0383
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal4/100Lower relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 4% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Observed multi-stage progression
Risks and missing evidence
- Early development stage
- Long time in current stage