UK renewable project intelligence · REPD 04198
Abergorki Wind Farm
Thrive Renewables · Wind Onshore · Wales
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantThrive Renewables
RegionWales
CountyMid Glamorgan
CountryWales
Planning authorityRhondda Cynon Taf
Planning reference13/0663/10
CfD allocation roundAR6
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal82/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 82% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- CfD support recorded
- Observed multi-stage progression
Risks and missing evidence
- No major public-data warning detected