Gaineamhach Hydro Scheme Powerhouse

Hydroplan/Three Lochs Hydro · Small Hydro · Scotland

Reported capacity2 MWInstalled Capacity (MWelec) in the public REPD record
Development stageRevisedCurrent short status in the latest source snapshot
Screening score33/100Medium heuristic screening risk

Planning record

Project Evidence

Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.

TechnologySmall Hydro
Operator or applicantHydroplan/Three Lochs Hydro
RegionScotland
CountyHighland
CountryScotland
Planning authorityHighland
Planning reference16/03353/FUL
CfD allocation roundNot reported

Planning history

Planning Timeline

  • Planning submitted
  • Latest public record

Time to operation

Delivery Signal

Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.

Two-year signal15/100Lower relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
Ranking signal only · Moderate public-data coverage

The score is a percentile rank, not a 15% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.

Positive public evidence

  • Observed multi-stage progression

Risks and missing evidence

  • Early development stage
  • Long time in current stage
Source and scope. Project facts derive from the official DESNZ Renewable Energy Planning Database quarterly extract. Delivery signals and screening scores are research enrichments by this platform; public data does not reveal private finance, land, supply-chain or contract terms.