UK renewable project intelligence · REPD 06327
Longhill Burn Wind Farm
EnergieKontor UK · Wind Onshore · Scotland
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantEnergieKontor UK
RegionScotland
CountyWest Lothian
CountryScotland
Planning authorityWest Lothian
Planning reference0359/FUL/19
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Construction started
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal84/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 84% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
Risks and missing evidence
- Long time in current stage