UK renewable project intelligence · REPD 06519
Cardinghill Wind Turbine
Cardinghill Renewables · Wind Onshore · Scotland
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantCardinghill Renewables
RegionScotland
CountyAberdeenshire
CountryScotland
Planning authorityAberdeenshire
Planning referenceAPP/2017/2857
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal0/100Lower relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 0% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Planning consent recorded
- Observed multi-stage progression
Risks and missing evidence
- No major public-data warning detected