UK renewable project intelligence · REPD 06733
Cloiche Wind Farm
Scottish & Southern (SSE) · Wind Onshore · Scotland
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyWind Onshore
Operator or applicantScottish & Southern (SSE)
RegionScotland
CountyHighland
CountryScotland
Planning authorityScottish Government (S36)
Planning referenceECU00002054
CfD allocation roundAR6
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal83/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 83% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- CfD support recorded
- Observed multi-stage progression
Risks and missing evidence
- Long time in current stage
- Repeated capacity revisions