UK renewable project intelligence · REPD 06941
Chelveston Renewable Energy Park
Federal Estates · Battery · East Midlands
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantFederal Estates
RegionEast Midlands
CountyNorthamptonshire
CountryEngland
Planning authorityNorth Northamptonshire
Planning reference17/00784/FUL
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Construction started
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal100/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 100% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
Risks and missing evidence
- Long time in current stage