UK renewable project intelligence · REPD 07616
Down Barn Farm
Scottish Power Renewables · Solar Photovoltaics · South West
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologySolar Photovoltaics
Operator or applicantScottish Power Renewables
RegionSouth West
CountyWiltshire
CountryEngland
Planning authorityWiltshire
Planning reference19/10890/FUL
CfD allocation roundAR4
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal75/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 75% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- CfD support recorded
- Above-average developer track record
Risks and missing evidence
- Long time in current stage