UK renewable project intelligence · REPD 08220
Three Bridges Solar Farm
Pathfinder Clean Energy UK Dev Limited · Battery · Eastern
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantPathfinder Clean Energy UK Dev Limited
RegionEastern
CountyNorfolk
CountryEngland
Planning authorityBreckland
Planning reference3PL/2020/1134/F
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal97/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 97% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
Risks and missing evidence
- Long time in current stage