UK renewable project intelligence · REPD 09207
The Carrs - Meadow Farm Energy storage facility
BayWa r.e. · Battery · North East
Planning record
Project Evidence
Source fields are retained from the latest UK Renewable Energy Planning Database snapshot.
TechnologyBattery
Operator or applicantBayWa r.e.
RegionNorth East
CountyCleveland
CountryEngland
Planning authorityStockton-on-Tees
Planning reference23/0752/FUL
CfD allocation roundNot reported
Planning history
Planning Timeline
- Planning submitted
- Planning granted
- Latest public record
Time to operation
Delivery Signal
Relative two-year evidence for prioritisation, separated from unvalidated literal probabilities and external-risk scenarios.
Two-year signal98/100Stronger relative evidence
Three-year outputResearch onlyNot released as a probability
Five-year outputWithheldInsufficient validated cohorts
The score is a percentile rank, not a 98% chance of delivery. Use it to prioritise comparable projects, then inspect the dated planning evidence and constraints before making a decision.
Positive public evidence
- Construction has started
- Above-average developer track record
Risks and missing evidence
- Long time in current stage